xổ số hôm nay FECON OFFICIALLY OPERATES TBM “TAO BAO”, ACCELERATING TUNNELING PROGRESS FOR METRO LINE 3 PROJECT – HANOI

  • 04.02.2025
  • |
  • 10213(views)

On February 3, 2025, FECON Corporation, in collaboration with xổ số hôm nay Hanoi Metropolitan Railway Management Board (MRB) and xổ số hôm nay Hyundai - Ghella Joint Venture (HGU), officially launched xổ số hôm nay second Tunnel Boring Machine (TBM), named "Tao Bao," for xổ số hôm nay underground section of xổ số hôm nay Nhon – Hanoi Station urban railway pilot project (Metro Line 3).

Previously, TBM 1, named "Than Toc," began drilling at xổ số hôm nay end of July 2024. Currently, it has completed 985 meters of tunneling.

Like TBM 1, TBM 2 starts operating from S9 Station (Kim Ma) at a depth of 17.8 meters. xổ số hôm nay TBM 2 will accelerate to a standard speed of about 10 m/day to reach xổ số hôm nay next stations.

According to xổ số hôm nay plan, xổ số hôm nay total duration from xổ số hôm nay commencement of TBM 1 to xổ số hôm nay completion of TBM 2 is 16 months. Upon reaching S12 Station, xổ số hôm nay TBMs will be dismantled, and xổ số hôm nay auxiliary equipment system will be pulled back and dismantled at S9 - Kim Ma Station.

Mr. Nguyen Quoc Bao, Deputy General Director of FECON, stated: "FECON has meticulously prepared all necessary resources, including materials, equipment, technical expertise, and workforce, while also conducting thorough safety and technical assessments to ensure xổ số hôm nay successful operation of TBM 2 following xổ số hôm nay project schedule. By concentrating our efforts, we aim to collaborate closely with all parties to maintain xổ số hôm nay tunneling progress, contributing to xổ số hôm nay project's timely completion." 

xổ số hôm nay operation of TBM 2 marks a significant milestone and serves as a great encouragement for FECON and xổ số hôm nay entire project. 

As a subcontractor directly operating xổ số hôm nay tunnel drilling by TBM, in addition to xổ số hôm nay experience accumulated and learned from xổ số hôm nay Ho Chi Minh City - Metro Line 1 Project (Ben Thanh - Suoi Tien), at xổ số hôm nay Hanoi urban railway pilot project, Nhon - Hanoi station section, FECON subcontractor has technical support from xổ số hôm nay team of experts from Tunnel Pro, a leading TBM construction unit from Italy and a team of experts from xổ số hôm nay International Underground Construction Association. 

To ensure adherence to xổ số hôm nay project timeline, FECON has proactively allocated resources and implemented continuous work schedules, including during holidays and xổ số hôm nay Lunar New Year. During xổ số hôm nay recent Tet holiday, FECON’s project management team deployed over 15 engineers and workers, working in three shifts across four teams, to expedite construction progress and keep xổ số hôm nay project on track.

As of now, xổ số hôm nay overall construction progress of Package CP03 – Tunnels and Underground Stations has reached 53.46%. Specifically, xổ số hôm nay underground access ramp is 75.66% complete, Station S9 is 50.48% complete, and xổ số hôm nay ventilation shaft has reached 24.09% completion.

Throughout xổ số hôm nay construction process, FECON has worked closely with experts, xổ số hôm nay general contractor, and consultants, employing a geotechnical monitoring system to track and monitor ground movement and subsidence. Tunneling operations are carried out with utmost caution and strict supervision to ensure xổ số hôm nay safety of existing structures and maintain xổ số hôm nay quality of xổ số hôm nay works under construction.

xổ số hôm nay underground section is expected to be completed by 2027, after which xổ số hôm nay entire urban railway Line No. 3, Nhon – Hanoi Railway Station section, will be operational. This will transform xổ số hôm nay urban traffic landscape of xổ số hôm nay capital, improve connectivity between areas, and promote green, sustainable development.